How to size a battery bank for load shedding

Zing LV and HV battery range

Inverter size decides what you can run. Battery size decides how long you can run it. They are separate decisions and sizing one does not size the other.

Step one: how much are you drawing?

Add up the wattage of everything you need running during an outage. Not everything in the house - everything that genuinely has to stay on.

Say that comes to 1,500W. That is your draw.

Step two: for how long?

Multiply your draw by the number of hours you need to cover. This is where watts become watt-hours, and the distinction is the whole game.

1,500W for 4 hours is 6,000 watt-hours, or 6kWh. That is the energy you need out of the bank.

Step three: allow for depth of discharge

This is the step people skip, and it is why banks come up short.

You should not plan to drain a battery to zero. Zing's LiFePO4 batteries are rated for 90% depth of discharge, so a bank's usable energy is about nine tenths of its rated figure.

For 6kWh of usable energy at 90%, you need roughly 6.7kWh of rated capacity. In practice you would round up to the next size rather than sizing to the exact edge.

Matching that to real batteries

Capacity in kilowatt-hours is volts multiplied by amp-hours. Across the Zing 51.2V range:

  • 100Ah - 5.12kWh rated
  • 200Ah - 10.24kWh rated
  • 300Ah - 15.36kWh rated
  • 400Ah - 20.48kWh rated
  • 600Ah - 30.72kWh rated

So the 6.7kWh requirement in our example lands on the 200Ah, with comfortable margin.

Step four: check it can recharge in time

A bank that cannot refill between outages is a bank that gets smaller every day.

Two things set the recharge rate: how much solar you have, and how fast the inverter can push charge into the battery. Zing's inverters publish a maximum charging current - 120A on the 6KW IP54, 160A on the 10KW IP54, rising to 280A on the 15KW three phase - and the battery has its own limit. The lower of the two is what you get.

You do not have to buy it all at once

The 51.2V batteries support up to 15 units in parallel. That means you can install what you need now and add to the bank later as budget allows, rather than over-buying on day one for a load you might never reach.

It is worth planning the first purchase with that in mind - leaving physical space and cable capacity for a second unit costs nothing at installation and a great deal to retrofit.

A sense-check on the whole system

Three numbers should be in proportion: the inverter's output, the battery's capacity, and the solar array feeding both. A large battery behind a small array charges slowly. A large array behind a small inverter wastes panels.

If you want to work through all three together, start with sizing the inverter, then come back to the battery.

Want a second opinion on your numbers? Send them over and we will check them with you.